KENTUCKY PETROLEUM LP
Videos
Durham day #1 workover
Day 1 of the re-completion of the Durham #1 well consisting of shutting-in the well, final location preparation work, rigging up the service rig, moving the pump jack away from the well head and beginning the removal of the rods.
Durham day #2 workover
Work completed includes finishing pulling rods and production tubing, unloading the casing delivery, digging s pit with a mini-excavator, bailing the well, and positioning the water tanks for the cement job.
Durham day #3 Recompletion
Tuesdays work included running 3425.8' fo 4.5" casing, expanding the pit, finishing filling the water tanks and cementing the casing in place in the well bore.
Durham day #4 Recompletion
Today's work consisted of drilling out the concrete plug, the pack off shoe, running a sand pump to clean the well and then bailing the well.
Compressor Station Upgrade - September 8, 2011
A new compressor unit was installed in order to increase processing capacity to accommodate the increased natural gas production.
Sulfridge Well post Acid job – September 27, 2011
After the acid job was completed we ran the swabbing tool 6 times. This is one of the later swabs, which resulted in mostly oil with a small amount of water mixed in.